Nairobi, Addis in landmark 400MW power purchase deal

Share Bookmark Print Email
Email this article to a friend

Submit Cancel
Rating
Details of the high-stakes negotiations before Kenya signed a 400MW electricity deal with Ethiopia two weeks ago are emerging, revealing that Nairobi managed to talk down the initial charges proposed by Addis Ababa as too high.

Details of the high-stakes negotiations before Kenya signed a 400MW electricity deal with Ethiopia two weeks ago are emerging, revealing that Nairobi managed to talk down the initial charges proposed by Addis Ababa as too high. 

By KENNEDY SENELWA  (email the author)
Email this article to a friend

Submit Cancel


Posted  Sunday, January 22  2012 at  15:34

Details of the high-stakes negotiations before Kenya signed a 400MW electricity deal with Ethiopia two weeks ago are emerging, revealing that Nairobi managed to talk down the initial charges proposed by Addis Ababa as too high.

The deal, which analysts say presages a new era of power trading in the region, was arrived at after a great deal of haggling, with the Ethiopians pressing for a higher price on the grounds that Kenya is currently buying even more expensive power from thermal plants.
The deal ushers in one of the biggest power pool projects in the region, and will serve as a model for future arrangements under the Eastern Africa Power Pool.

The deal is a take or pay contract, meaning that Kenya has to pay for the 400 MW supply even if it is not using it.

It will pay US cents 7 per kilowatt hour. The transmission line is expected to be completed by 2016 at a total cost of $1.2 billion.

The agreement for continuous supply of 400MW was concluded in Addis Ababa by Kenya Power and the Ethiopian Electric Power Corporation after two days of intense negotiations from January 6-8.

The power purchase agreement is the second in Kenya’s history as it seeks long term solutions to its perennial power problems. A decade ago, Kenya imported about 30MW from Uganda.

Share This Story
Share

The conclusion of the agreement paves the way for Kenya and Ethiopia to mobilise funds for building a 1,045-kilometre high voltage electricity transmission line. Ethiopia, which is endowed with a huge hydropower potential of about 45,000 MW, is currently building three dams to generate power for domestic use and export to Kenya and other neighbouring countries.

Other projects under the Power Pool are under way, with the goal being to create a regional electricity network.

Tanzania will be connected to its neighbours through the planned Kenya-Tanzania interconnection and through the extension of the Tanzania grid to the northwestern Rusumo Falls Hydropower Project shared among Burundi, Rwanda and Tanzania. Meanwhile, Uganda and DR Congo are planning to extend the Ugandan electricity network to Beni and Bunia in DR Congo through a transmission line, Nkenda-Beni-Bunia.

According to the Kenya Electricity Transmission Company (Ketraco), Agence Française de Développement (AFD) of France, the African Development Bank and the World Bank have expressed a commitment to funding the Kenya-Ethiopia project.

Ketraco was a few years ago hived off from Kenya Power to exclusively build infrastructure for high voltage transmission. Kenya Power as a distributor is in charge of smaller voltage lines for connecting end-users.

Ethiopia is the only country in the region with surplus power, backed up by by a reserve margin of more than 30 per cent, double the recommended margin of 15 per cent. “Donors like the French are keen to support the transmission line project.

Kenya’s funding is about $666 million and Ethiopia’s $486 million,” said Ketraco managing director Joel Kiilu. He said selection of consultants to oversee building of the transmission line, designed with power transfer capacity of 2,000MW, will start soon and construction work begins in mid-2013 with a completion date of 2016.

The high voltage direct current (HVDC) line requires putting up of steel towers, transmission cables and inverter substations at Suswa in Kenya and Welayta Sodo in Ethiopia. The HVDC line will start from Welayta Sodo and run south along Lakes Abaya and Chamo, through Konso and cross the Kenyan border about 90 kilometres west of Moyale town.

From Moyale, the transmission line will run through Marsabit, Samburu, Laikipia, Nyandarua and Nakuru counties to terminate at Suswa. Kenya and Ethiopia have formed a joint project co-ordination unit (JPCU). Ketraco is finalising bid documents and tenders are to be floated in April.

1 | 2 Next Page »

Add a comment (1 comments so far)

  1. Submitted by nesh999
    Posted January 29, 2012 11:03 PM

    Bad decisions by the idiots incharge will make us always suffer. Kenya has peotential to generate enough power for domestic use as well as for export. Our geothermal has not been well exploited and it would be better to invest the $1.2bn in this.

.

IN PICTURES: Congo clashes

In a hand-out photograph released by the African Union-United Nations Information Support Team May 2, 2012 outgoing African Union Mission in Somalia (AMISOM) force commander Major General Fred Mugisha (left) prepares to hand over command to his successor, Ugandan Lt. General Andrew Gutti (right) at a ceremony at the mission's headquarters in the Somali capital, Mogadishu. Mugisha had commanded the AU force since early August 2011. Photo/AFP

AMISOM handover

Malawi's late president Bingu wa Mutharika's supporter wears a "Bingu rest in peace" tee-shirt as he stands in front of the Mpumulo wa Bata Mausoleum during his funeral at his Ndata farm residence in the district of Thyolo, southern Malawi, on April 23, 2012. Photo/AFP/Amos Gumulira

Final send off for Mutharika

Sudanese carry an Armed Forces officer as they gather outside the Defence Ministry in the capital Khartoum on April 20, 2012 to celebrate retaking the oil town of Heglig from South Sudanese forces. Border clashes between Sudan and South Sudan escalated last week with waves of air strikes hitting the South, and Juba seizing the north's Heglig oil hub on April 10.  PHOTO/AFP/ASHRAF SHAZLY

Sudan celebrates retaking Heglig